BAKUBUNG WESIZWE ELECTRICAL INFRASTRUCTURE

CLIENT Wesizwe
ENGINEERS Worley Parsons
SCOPE OF WORK Complete Electrical, Control, Earthing & Lightning Protection installation & Commissioning.
1000v-33kv
Eskom tie in
Overheadlines, Solar Powered Street lights & all mine out buildings installations.
DURATION 10 months
VALUE R 13,300,000.00
CONTACT Johan Pretorius
TEL 011 218 3000
SITE MAN-HOURS 38500
PEAK MANPOWER 25
CABLE INSTALLED 25078m
RACK INSTALLED 615m
LIGHTS INSTALLED 184